On 15.11.2010 work could begin with the excavation of the foundation pit. For this reason, due to the special care near existing buildings, up to 3 weeks are planned.
Afterwards the ground slab can be poured (if there is no frost!).

All excavation materials are piled into so-called ‚Mieten‘ (mounds), which will be removed later.

From „Wikipedia“:
A Miete (from Latin meta «cone») refers to a specific storage form for bulk materials.
Mieten can be stacked in a controlled manner and form stable heaps. Using simple geometric shapes one can easily estimate the weight of the pile by its volume and density.

These mounds are differentiated according to various properties of the material, e.g., recyclability, storability, contaminant class, etc.
On our site the excavation is sorted, for example, according to whether the material can be recycled elsewhere or must be treated especially carefully for environmental reasons. This also applies to asphalt here.

At the corner of the site you can see a large pile of newly delivered sand/gravel.
This gravel is needed to immediately create a so-called „cleanliness layer“ on the ground and before pouring the ground slab.

To all classes: If there is really something to see on the construction site, we invite you to tours of the construction site, during which the on-site manager will explain to you what is currently being built and how!